After week 9

Sorry for the delay everyone in posting the progress from last week. I was away for the week at a property conference in Cannes and didn’t quite have time to get this out before I left on Monday afternoon.

This what the works looked like one week after their estimated completion date – we are almost there!  In the 9th week the following works were undertaken by our builders:

  • Original timber trusses re-installed in study (I like what they look like natural for now!)
  • Tiling around bath tub completed and grouted
  • Plastering completed over bathroom walls and ceiling
  • Plastering complete in hallway
  • Shower mixer installed (but not the shower head, so no showering yet)
  • Flat panel FD30 fire rated doors cut to size
  • Study door installed on its hinges
  • Installed the LED light strips in the hallway
  • Installed the LED light strips in the study on top of the trusses

On the weekend we got to work too and did the following:

  • Painted the primer base coat onto both sides of both doors with Johnstone’s Joncryl Primer Undercoat (yes, the same stuff that we used on the brickwork)
  • Painted the base coat onto the small portion of brickwork in the hallway
  • Painted the base coat on the hallway partitions
  • Painted the base coat on the hallway ceiling and around the hallway rooflight

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s