Right. So after that refreshing interlude, lets get back to some dusty construction progress photos of the bathroom!  This week the builders:

  • Installed cabling for the electric under floor heating mat
  • Started boarding out the partitions and around the skylight framing with plasterboard.
  • Agreed with us the final setting out positions for switches and sockets
  • Installed the sockets

It was as short 3 day work week again unfortunately, as they had commitments elsewhere. They have however promised that we will see big steps forward next week when the floor tiles go down and their plasterer comes in to plaster the partitions and brickwork. We can’t wait!

 

 

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s